GRIP I 40 - Central to Coors

News:

Governor Bill Richardson Cuts Ribbon on I-40 Paseo Del Volcan Stimulus Project

Crews Ahead of Schedule on Interstate 40 West Central Interchange ARRA Project

Governor Bill Richardson Breaks Ground on I-40 Paseo Del Volcan Stimulus Project

pic.

 

Sections Completed:

I-40 from Coors Boulevard to 98th Street; completed Aug. 2007

I-40 from 98th Street to W. Central Interchange; completed December 2008

I-40 Paseo del Volcan/W. Central Interchange (ARRA); completed June 2010

 


 

Project Information

The reconstruction of GRIP Interstate 40 between Central Avenue and Coors Boulevard will improve the condition of the highway and create a more efficient and safer path for drivers traveling through the area.

The first phase of the project, between Coors Boulevard and 98th St., is began summer 2006. That section, which cost about $15.5 million, was awarded to a contractor in June 2006, and completed August 2007.

The second phase of the project, between 98th St. and Paseo del Volcan, or West Central Interchange followed in January 2008. That work cost an estimated $17.5 million and was substantially complete by Decemeber 2008.

Proposed improvements to the 5.6 mile stretch of the two phases of the project include new pavement, road shoulders and the construction of a westbound climbing lane the 98th St. Interchange.

The final phase of construction began on June 8, 2009, and consisted of rebuilding the West Central Interchange. The old interchange at West Central was functionally obsolete and required major improvements. Additionally, this interchange provides access to the Double Eagle Airport and the area is experiencing increased development. The improvements include reconstruction of the interchange to serve the current needs and accommodate the growth potential. 

This project required partnership with various entities including the City of Albuquerque, Counties, and others. The approximately $27 million project was funded through the American Recovery and Reinvestment Act and was completed in June 2010.